Snettisham
2009 - 9: The Ceiling
August 28-30

The ceiling and attic hole
It
was late August and I hadn't made much progress at the
homestead since early July. It's not that I'd been idle--the
weeks
between had seen the Icy Strait trip, Sweetheart Creek, a weekend up
the Taku,
and brought Chris and my family down to Snettisham on separate
occasions.
But, needless to say, I was getting antsy. The new deck
construction had
gone so well in the spring that at the time I thought I'd exceed my
modest
expectations for summer construction, but I hadn't even started my only
other
major task, the ceiling. It was a task worthy of putting off,
involving a
lot of overhead work fighting with tongue and groove panels and I
wasn't
anxious at all to nail in all those soft finish nails. I hoped to
get
back up the Taku the following weekend on one of the few high tides
left in the
summer, so was extremely anxious to make it down to Snettisham Friday
after
work to make some progress .
Thus I paid close and nervous attention to the forecast all week, which
went
from four to three to four to five foot seas by Friday morning
predicted
in
Stephen's Passage. One of my coworkers gave me her husband's
number at
the NOAA weather center in

The seas moderated a bit, especially in the lee of Point Arden, then
built
again as we crossed to Grand. We hit a few genuine three footers
when we
left the lee of Grand for Grave Point, but that was the last of it.
From
Grave Point south the seas laid down to almost nothing and whales
appeared,
first in front of
The next morning I got up around 8:30 and made my way to the lodge to
get
ready. The lodge smelled of
propane, which
I suspected might be an indication that the propane tank for the gas
lights was
low. First I organized the stacks of panels I'd put on the top
porch
the last
time, then when Chris arrived I headed out the back to replace the
propane tank. It's
well-protected inside the bear-proof box, but its placement behind the
propane
tank for the range (which sits about twelve inches higher on two stacks
of
cedar panel scraps) makes it very awkward to work on and I could not
tighten
the fitting enough to stop it leaking. Every time I turned on the
tank
I
smelled gas. My back ached from bending over and cranking on the
wrench
and my frustration was mounting. I kept checking for leaks along
the
fittings for both tanks, but nothing else seemed to be a problem.
Chris
came out to help and hold the flashlight for me, but I was almost too
upset to
speak. In the end it was a simple fix. I'd embarrassingly
neglected
to check the connection between the copper tubing and the regulator;
when I
finally drizzled some soapy water on it, big bubbles hissed out.
A little
wrench work and the system was set up.
The ceiling had its own endless frustrations. Chris and I went up
and
down the two step ladders ad nauseum and we both finally donned shoes
to keep
our feet from aching from the metal treads. We followed a panel
pattern
on the ceiling that I'd come up with on a previous trip that avoided
adjoining
seams on consecutive rows and made use of four, eight, and twelve foot
boards. If only they all went up as easily as the four foot
boards! We
placed the four footers on either end of rows that made use of an eight
and a
twelve footer and they went in so easily I was able to put them in
myself. The eight footers were a little more work. The
general
scenario was this: Chris and I set up our step ladders on either
end of
the where the board would go, placed the board on top, and climbed
up ourselves.
We'd hold it in place against the ceiling while I pounded the groove at
the end
of the board around the tongue of the previous board with a rubber
mallet.
If that worked, we'd put a single nail in to hold it in place and allow
the
board to pivot. Once in a great while, the board would fit well
and we
could trade the mallet back and forth, quickly pounding it into
position, but
that was rare. More often I'd leave the board in place and
reposition the
ladder in the center of the board where it crossed a seam. Seams
were the
source of most of our problems, as the tongues of the neighboring
boards were
often at different levels, or perhaps one wasn't pounded as far over as
the
other. Sometimes a lot of pounding would work, sometimes I'd have
to pry
one of the boards down to meet the other, and more often than not, all
of this
work would cause the single nail to pop out. Then Chris would try
to pound
his end in while I held up the board and we'd start all over. We
frequently had to go back
and
forth several times before we got the entire board to line up and wrap
abound
the tongues correctly, moving the ladder between the middle and the end
as
needed.
The
twelve footers were much worse. They were long enough that we
always
had to move the ladders just to get started and required the paddles
I'd
created
earlier in the summer--two 2x2s with a flat board on one end to help
hold the
panels up. The twelve foot panels were so long that they'd sag in
the
middle and required support for us to work on the ends. So we'd
mount our
ladders to hold the panel in place and I'd grab the paddle that I'd
placed
nearby and wedge the panel against the ceiling. Then I'd come
down and
use the
second paddle to hold the middle section up so Chris could pound one
corner in
and nail it. Then I'd reposition the ladder in the middle (I
think) and
deal with the seam, then work on the end. There was usually a lot
of back
and forth and many frustrating moments. We came to loath the
twelve
footers. They'd seemed like a good idea, both to vary the pattern
and to
take up more space with a single board, but it would have been far
faster to
use multiple small boards and we were happy enough when we ran
out.
I should take a moment to talk about the nailer. One of my
hesitations in
taking on this project was the agonizing thought of trying to nail the
boards
in overhead by hand--those finish nails are ridiculously difficult to
deal
with. Compressors had been tried the summer before and failed, so
I
didn't think a nailer was possible. Thankfully, I chatted with my
boss
about the project on Thursday and he offered up his cordless Dewalt's
finish
nailer. It was amazing. Heavy to lug up and down the
ladder, but
amazing in its effectiveness and efficiency. I don't know how we
could
have progressed without it. The only downside was that poor Nigel
didn't
enjoy the percussive sound of the nail gun and fled as soon as the door
was
opened. He spent some time down on the new deck as well as on a
towel I
put out for him on the covered deck. He also did some wandering
and
disappeared for a long time in the afternoon (we think he was holed up
on the
porch of my cabin to avoid the noise).
So we slowly progressed, going between rows of three eights, to
twelve-twelves,
to eight-twelve-fours, to four-twelve-eights, back to three eights, and
so
on. It was hard work. We had boards and mallets fall on us,
paddles
crashed all over the place (thankfully not destroying either of the
propane lights),
and it seemed to move at an agonizingly slow pace. The room
became
annoyingly cluttered as we moved the couch and other items around to
facilitate
the ladders. After lunch we took a break from the ceiling and I
began
spontaneously to organize the items that had been stashed between the
wall and
the couch, including a basket of gloves and a box full of miscellaneous
screws
and nails. I spent some time carefully combining like fasteners,
transferring those in deteriorating paper bags to ziplocks or small
plastic
tubs. I can't believe how many screws and nails I have down
there!
When I was done I had a very tidy box of bags and boxes and had cleaned
and
organized all the other items stashed in that area. Outside, I
collected
a box of pallet firewood and put it inside to stow later, then walked
over to
firewood staging ground and moved the stack of uncovered, larger rounds
under
the same tarp as the smaller rounds and the split firewood and secured
the
tarp for
the winter. Back inside, I sat down and rested a little while I
developed
a design for the rest of the ceiling to take into account the future
trap door
to the attic and the diminishing supply of twelve footers.
I have a nice, if modest, attic above the lodge. I'd had the
foresight to
occupy it with a bunch of scraps of plywood for storage and
floorboards.
Earlier in the day I'd cut a hold through the visqueen in the center of
the
room, choosing the area with the most head space (about three feet) and
with
access to the greatest area for storage. I had to recalculate the
lengths
of boards to go around the opening and now needed to design a new
pattern for
the rest of the ceiling. Because it had been pouring rain all day
(steady, heavy rain, the remnants of a typhoon) I'd set up a board
cutting
station on the top porch where we cut boards that needed to be trimmed
and also
measured and cut the oddly-lengthed boards 
to
go around the trap door
opening. Some time around 7:30 we got to work on the ceiling
again.
Although I'd been realistic in my expectations, I was still a little
disappointed by the progress and was grateful that things seemed to
pick up
speed later in the day. We were hard at it and beginning to place
boards
along one edge of the attic opening when we struggled against a warped
panel
and I hit a wall. It was 9:00 pm and I'd been working solid for
twelve
hours. Now that we'd made it about half way across the ceiling,
we
returned the couch to its normal position, this time placing four
stacks of
short cedar panels under it to raise its height and improve the view
out the
picture window. The ceiling looked amazing, though we'd
periodically
noticed that whole sections sagged alarmingly (mostly near the wall
where the
boards weren't always long enough to nail the ends to the joist).
Some of
these we'd secured earlier in the day, pounding them up and nailing the
heck
out of them, others I fixed the next morning. Once we'd
cleaned up a
little, I made pasta and vegetables for dinner and played a little gin
with
Chris before calling it a night. Oddly, I was dealt one amazing
hand
after another and didn't seem able to lose, which is quite unlike me.
![]() Nigel escaping the rain on the porch |
![]() Nigel exploring down the beach |
![]() Working on the second row |
The next morning saw a break in the rain and
everything was
still. I
slept in a little, then started working around 9:30, continuing my
efforts to
organize the lodge. Why I hadn't thought to use the attic before
I don't
know, other than that I had a weird, unconscious belief that I needed
to wait
until the ceiling was finished before it would be functional. Now
that
I'd cut through the visqueen and stuck my head into the cool, spacious
area, I
was anxious to make use of it. One of the most frustrating and
depressing
things about the lodge to me is the constant clutter, every wall lined
with
crap, often in disarray. At least once a trip I give up searching
for
something that I know I have somewhere nearby because I can't bear to
dig
through the mess anymore to look for it. So I was on a
mission. I
unpacked a box of extra dishes that I'd had for years, organized the
kitchen area
and the kitchen tote (removing useful items I'd forgotten I had and
replacing
them with unused items, using an old frying pan to hold all the loose
silverware, cleaning up the canned goods shelves, etc.), and organized
everything along the wall between the kitchen and the front door.
I
discovered that the paint cans and the food tin were rusting onto the
floor, so
I swept and cleaned underneath then and put down pieces of
visqueen. I
sorted and organized my enormous box of miscellaneous crap along with
the tool
bucket, replacing the cardboard box with a tote and putting the
majority
of the
rarely-used tools in another tote, leaving only the commonly used ones
and
small ones in the bucket. In the process I found most of the
things I'd
been digging for all summer. Those items that aren't used
regularly I put
aside for storage in the attic. These included rolls of felt, a
toilet
seat, visqueen, flashing, hardware cloth, stove pipe, painting
supplies, water
jugs, steel connectors, joist hangers, and scraps of insulation.
It was
immensely satisfying to store these tidily in the attic, leaving a much
improved and neater lodge (see photo below of the sorting mess).
Chris
came over in time to help me stow the large and awkward items upstairs,
then we had a little breakfast and started back on the ceiling.
Finishing
the ceiling was out of the question, so I proposed that we complete the
rows on
either side of the attic entrance and the first row all along the other
side. It went relatively well and, thankfully, the first long row
(three
eights) connected the two sides flawlessly. I was pretty nervous
working
above the propane light on the back wall, but it made it through
undamaged. The ceiling panels looked lovely and, once again,
brought the
lodge a giant step closer to completion. Please don't look too
closely,
though. Too many of the seams between panels in the same row have
awkward
gaps, most of them isosceles triangles where I'd failed to cut the end
of one
of the boards square. I hope that filling them with sealant some
day will
fix the problem, and you'd really have to be looking hard to
notice.
By this time is was early afternoon and time to pack up for a 3:30
departure. When my chores were done, I kayaked out to the
boat.
Ordinarily I like to fuel the boat and bail it while at anchor, but the
tide
was falling to a particularly awkward stage and I wanted to make sure
we could
get out. I brought it to shore up the deep channel and suggested
to Chris
that we
load
the boat as hastily as possible, which we did, placing all
the
gear in the bow or on the stern bench to avoid the water. The
typhoon
rains had
filled the boat and water rose above the floorboards all the way
forward to the
steering console, which didn't help the weight issue. (The tides
were
moderate that weekend and the boat never went aground to allow me
to pull the plug and drain
it.) When Nigel was aboard I shoved off and we floated briefly
before
going aground again. The wind was pushing us against shore
and I was
forced to jump out, flooding my xtratuffs while I pushed and
pushed
and pushed to no avail. Desperate, I finally called Chris out and
he too
went in over his boots, but together we were able to push ourselves to
deep
water. We motored beyond the drop-off, then stopped. I
refueled
while Chris heroically did the majority of the bailing. We stowed
our
gear more appropriately, emptied our boots, and took off.
The trip back was wonderfully calm. We stopped at the Seal Rocks
for a
whale that was swimming through the kelp. When he swam toward
Admiralty we
slowly made our way through the cut between the mainland and the rocks,
noting
that the kelp was pulled strongly north with the falling tide. A
lone
common loon (not a common bird in Southeast!) dove near the rocks and I
stopped
for some photos. Chris then spotted whale blows toward Admiralty,
so we
headed in that direction, passing a single whale on the way. I
either
misjudged where the whales were or we never saw them again, but two
more came
up half way to
![]() Nigel and Chris taking it easy |
![]() The attic hole |
![]() Items stowed in the attic |
![]() A somewhat more tidy lodge |
![]() Water in the boat |
![]() Common loon at Seal Rocks |
![]() Whale |
![]() Whale |
![]() Red-necked phalaropes |
![]() View from the front porch |